|

Coe
Press Servo Feed
Equipment Boosts Production
By 66% and Slashes Setup Times
for Cylinder Manufacturer

Just like
the cylinders that they produce, their manufacturing process was under
pressure. By replacing its outdated air feeds and coil handling equipment
on one of their stamping press lines, Manchester Tank and Equipment Co.
(Elkhart, IN) reduced manpower; increased production; and slashed setup
times.
Manchester
Tank and Equipment Co. was founded in 1945 and is the largest North American
manufacturer of cylinders and tanks for propane, chemicals and compressed
air. Products produced at their Elkhart plant include Department of Transportation
approved steel and aluminum cylinders ranging from 1.4 to 28 gallons.
Customers and applications include original equipment manufacturers, gas-grill
producers, recreational vehicles, air compressors, forklift trucks, fire-suppressant
systems, refrigeration equipment requiring chlorofluorocarbon recovery,
and rail cars.
Manchester's
aluminum line of cylinders are primarily used as fork lift tanks with
an average run for any of the different cylinder sizes of about 300 a
shift. Roughly 7,000 cylinders a day of all sizes are produced in two
assembly manufacturing lines.
Steel
cylinder tops and bottoms are round blanked on a stamping press and drawn
into larger cup shapes. The tops are assembled from two parts, and have
multiple holes already stamped into the pieces to attach the valves in
a later operation. Even though most of the welding is done by automated
machines at Manchester, and the company builds most of its own equipment
for this, a manually operated spud welder is used to weld the valve fittings
to the cylinder's top.
Major
Stamping Improvements Realized
Steel and
aluminum cylinder fabrication begins with flat steel coil or steel coil
stock with a thickness ranging from .082" to .130" for blanking
or drawing. To produce the cup shape of the tanks, the operation uses
three 300-ton hydraulic presses for forming and one 400-ton mechanical
press for blanking. One of the presses punch the blanks from coil stock
and then draws it into cup shapes. A hydraulic blanking press is fed by
a cross feeder that moves the coil stock back and fourth in a zigzag motion
to get the maximum amount of metal from the coil. Then secondary operation
presses draw the metal, punch holes, and produce flanges. These cupped
pieces are then cut on the bottom in trimming presses to even out the
lips and any irregularities in the bottom that were caused in the drawing
process. The pieces are then formed to put a flange in the bottom of one
of the cup halves so that the top and bottom pieces will fit together
later when they are pressed together and welded.
Manchester
needed to boost production, cut setup time, and reduce manpower on a stamping
line that was using a 300-ton, variable-speed mechanical Minster press
to produce a 44" long part that is blanked, shaped into a ring and
used on the bottom of the tank for stability. This steel part is produced
in a 2-stage progressive die. To do this, they decided to eliminate their
air feed and coil handling equipment, replacing them with servo roll feed
and coil handling system from Coe Press Equipment (Sterling Heights, MI).
Operations Manager Jerry Burton said they installed a Coe coil handling
and feeder system in April, 2003. In this operation they immediately increased
productivity by 66%.
Previously,
an air feed had to grip the stock for this part three different times
to get it through the press. Burton said this hurt quality and production
speed. "The new Coe servo feed was capable of moving the stock through
the press with one feed stroke and allowed us to continually run our press."
He adds,
"With the air-feeder inconsistencies, the fastest that we would run
a product would be 30 strokes a minute, probably running high 70's low
80's in our efficiency percentage. Now I can run at 50 strokes a minute,
a 66% increase in production and well above 100% to 110% for efficiency."
To get this
productivity, Manchester purchased a CPRF-S224 ServoMaster Series 2 Roll
Feed (for up to 24" wide stock), a CPTT 2410 threading table, a CPPS
250 24 power straightener and a CPR-PO coil reel and coil car with a 10,000
lb. capacity.
Coe's servo
feeder also helped Manchester with set up speed by minimizing adjustments.
"We can actually adjust the servo feeder on the fly. With the air
feed, we would have to shut down production, manually measure the part's
length, adjust the air feeder and tighten the feeders grippers back down,
and check to see if we were within tolerance," remarked Burton.
With the
air feeder, their average changeover could take half an hour. Coe's Servo
Feeder lets them changeover in about five minutes. "Everything is
programmed into the SmartPac controller. We just punch in the product
number, and automatically bring up the coil-feed progression."
Coe's equipment
has saved Manchester one man per shift and they were able to cut back
to one shift. Also, since they never had a coil car before, this equipment
has allowed them to reduce the crane and operator time used to move coils.
"We are able to pre-stage our coils on the coil car to keep a job
running more efficiently or pre-stage for the next job. Now an operator
just needs to advance the coil car onto the reel," Burton added.
A threading
table has helped them manage their coil threading process. "Our operator
had to lift the coil from the floor into the air feeder. Sometimes heavier
coils needed two operators to do it safely. The threading table has made
it a one-man operation. He just needs to guide the coil into the feeder
speeding our process up tremendously."
Another
important feature of the Coe equipment is the feedroll pilot release.
Burton said, "The pilot release is a necessity with progressive dies.
Before the Coe equipment, we just had a manual limit switch adjustment
for it. The Coe equipment is all programmable and more consistent in opening
the rollers and allowing us to align the coil easily. This allows for
any setup inconsistencies, and lets us speed up our process, because we
know exactly when the rolls are going to open up for the pilot pin to
do its job and align the coil."
On the Coe
stamping line, foot rings and collars are produced along with a flat forklift
collar that is used on all of their steel forklift tanks. Job changeovers
are done two or three times per shift. Depending on the product, lot size
is anywhere from 2,000 to 10,000 per day. Foot rings are the companies
largest lot size, because they are used on all their products.
Putting
It All Together
During assembly,
the top and bottom tank pieces are pressed together with 800 lbs. of pressure
and tack welded. These pieces have been pre-flanged for a press fit. After
the tack weld they are set on a conveyor. Cylinders are then placed in
an automated seam welder with a laser aligning/tracking system that automatically
joins the halves using TIG welding (MIG for steel). This system with controls
by Jetline Engineering has a laser optical camera that follows the seam
of the two pieces and perfectly welds it with the process displayed on
a TV monitor. The foot ring (allows the cylinder to stand up) and top
collar (a shield for the valves and integrated carrying handle) are also
attached at this time.
Some cylinders
have a rough mill finish while others have a smooth one produced by shot
blasting for cosmetic purposes. These cylinders are pressure tested at
up to two times their service pressure, which can be up to 800 PSI for
some designs. Each cylinder's tare weight is then written on it in an
automatic process using a Telesis Pin-Stamp marking system. Next, the
cylinder is low-pressure tested at about 200 lbs. of pressure and checked
for leaks. They are then cleaned, have their valve-covers installed, powder
coated, and have safety and instruction stickers added before they are
placed on a pallet for shipping.
For steel
cylinders, the process is the same with automatic welding used whenever
possible for better welds. One of the differences in this line is that
the empty cylinder weight is stamped on the side according to DOT regulations.
Cylinders are also annealed in an oven (temperature about 1150 degrees)
to even out the steel's strength.
Currently
Manchester is working towards a lean manufacturing facility using a three-year
plan. They have three buildings in Elkhart, IN producing parts, and they
want to move all of the equipment from these facilities into one plant.
They are focusing on reducing inventory while producing products faster,
better and smarter.
Back
to Top
|